Tuesday, August 18, 2009

Concrete has been poured



Concrete has been poured on the new roof and on the 3rd floor. Window frames will be installed in a few weeks. The pouring of concrete has been poured at the new main entrance.

Currently there are 35-60 construction workers on site at Douglas County Hospital every day. This includes contractors for the following specialties: carpenters, sheet rockers, iron, concrete, roofing, electrical, plumbing, sheet metal, dirt, brick and a project manager.